1 - Free standing walls
2 - Walls connecting floor and ceiling
3 - Finishing
|
| 3 - FINISHING |
| |
| Leave to dry for 24 h before applying mortar joint or silicon finish*. |
| |
 |
|
 |
|
Always seal the joints in contact with the wall, floor and ceiling with silicon.
Once the finish has been applied clean the surface of the blocks. |
| |
 |
|
Glue a plastic, wooden or metal profiles for a neat finish. |
| |
 |
|
The structure achieves maximum resistance after three weeks. |
|
Remark: finishing material is not included in the Installation Kit
* LGA certificate for a wall with mortar joint finishing and SEVES's glass blocks.